Lilium Reaffirms 2026 Target for First Customer Deliveries, Delays First Manned eVTOL Flight to Early 2025

Editor

Lilium’s first aircraft will be used exclusively for ground testing starting in a few weeks, and its second aircraft will perform its first manned flight in early 2025.

(Munich, Germany) Electric vertical take-off and landing (eVTOL) vehicle developer Lilium today both confirmed its planned delivery schedule – with the first customer deliveries of its Lilium Jet targeted in 2026 – and announced the delay of its first manned eVTOL flight, which was previously scheduled for later this year, to early 2025.

PremiumEdition_Flyover_Forest (2).jpg

Rendering of Lilium’s electric vertical take-off and landing vehicle (eVTOL), the Lilium Jet, in flight, courtesy of Lilium.

According to today’s press release from Lilium, the confirmation of information and timeline details is based on a recent program review that considered the testing and validation requirements needed prior to Lilium’s first manned flight as well as the readiness of the company’s support organization and training devices for customers.

Per Lilium, the delay in the planned target date of the Lilium Jet’s first manned flight is due to indirect effects of ongoing industry-wide supply chain constraints.

The shift in timeline “has no material impact on customer deliveries, program planning, or total program costs,” reads Lilium’s press release.

Assembly of the third Lilium Jet, MSN 3, will begin later this year and the aircraft will join the certification flight test campaign in 2025, according to Lilium.

Lilium is currently building its first two aircraft at its production facility in Gauting, south of Munich, Germany; the company is also working with FlightSafety International in developing an engineering simulator that will be delivered early in 2025, according to Lilium.

Specific timeline details released by Lilium are as follows:

  • “First aircraft (Lilium Jet MSN 1) to be used exclusively for ground testing starting in a few weeks
  • Second aircraft (Lilium Jet MSN 2) to be used for first manned flight in early 2025, will start ground testing in the fall, soon after MSN 1
  • Three aircraft in production by year-end
  • Full structural aircraft for static tests available in fall
  • Engineering simulator developed by FlightSafety International to be delivered early 2025
  • Lilium prepares operational support with Flight Crew Training Simulator and Lilium POWER-ON, its support and services organization”

Lilium Chief Executive Officer Klaus Roewe commented: “Lilium continues to make significant progress towards entry into service of its Lilium Jet, not only on certification but also training devices and support and services for our customers. Our latest program review highlighted that our plan for 2026 first deliveries is confirmed despite the new timeline for the first flight, with no material impact on customer deliveries. With EASA, we continue to be working on the highest safety level of our product and we are ramping up production of our test aircraft. We also want to announce by year end the 2026 launch location of the Lilium Jet with one of our customers."

The FLY Report, delivered

The day’s aviation, space and future-flight headlines, straight to your inbox.
Continue with FLYJETS

From aviation intelligence to aviation access.

Explore charter availability and empty-leg opportunities on the FLYJETS marketplace.
Explore FLYJETS